Sheerwater Regeneration Authorisation of Further Building Phases
Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
Consequential to the decision of Council on 13
February 2020 which approved the financial framework for the
Regeneration of Sheerwater.
Decision:
Authorise Thameswey Development Limited to
undertake the construction of the Red, Copper and Yellow phases of
the approved Sheerwater Regeneration.
Authorise the acquisition by Thameswey Housing Limited of the
affordable homes completed in the Red, Copper and Yellow
phases.
Reasons for the decision:
To progress the implementation of the
Sheerwater Regeneration Project.
Alternative options considered:
None
Reason Key: Likely to result in significant expenditure/savings & affect significant proportion of Borough.;
Declarations: None
Contact: Ray Morgan, Chief Executive 01483 74333; Email: ray.morgan@woking.gov.uk Email: ray.morgan@woking.gov.uk.
Publication date: 07/12/2020
Date of decision: 04/12/2020