Decision Maker: Assistant Director (Place)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
CONTROL OF POLLUTION ACT 1974, s. 61
Approval of additional hours for noisy
construction work granted by EH Manager, Emma Bourne, to Sir Robert
McAlpine (SRM) from 20 February 2021 to 01 September 2021 for works
to the Lockfield Drive junction to Victoria Way, up to Goldsworth
Road junction/bridge and at the junction of Forge End on Victoria
Way and Church Street West. Hours granted include; 18:00 to 02:00
on Monday to Fridays and 08:00 to 18:00 on Saturdays.
Additional hours are for the purpose
completing Section 278 works for road, paving, signals and drainage
improvements at the above mentioned site(s).
local residents and businesses will be informed of the works prior
to commencement and will be provided with a site contact number. It
is also understood that SRM will be conducting on-going noise,
vibration and dust monitoring and will continue to co-operation
with their Local Authority and local residents to reduce the impact
of noise disturbance. Additional measures will be taken to minimise
the noise, including; use of acoustic panels and equipment
silencers, and steps will be taken to ensure plant is not left
idling running when not in use and deliveries are made during day
shifts, as far as is practically possible.
overnight noisy works have been operating for an extensive period
now and we have had no / very occasional complaints (those that
have come in have ended up being investigated and attributed to
other nearby development works). There is also encouragement to get
this work progressed as quickly as possible following delays caused
by the earlier lockdown period of the pandemic. Regular site
meetings with SRM confirm on-going noise, vibration and dust
monitoring and co-operation with ourselves and the local
residents.
Option 1 -
Option 2 -
Option 3 -
Declarations: None.
Contact: Emma Bourne, Environmental Health Manager Email: emma.bourne@woking.gov.uk Email: emma.bourne@woking.gov.uk.
Publication date: 18/01/2021
Date of decision: 14/01/2021