Decision Maker: Assistant Director (Place)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Control of Pollution Act 1974
Approval of prior consent for the completion
of out of hours (weekend) construction work on Bunyard Drive,
Sheerwater, (outside number 91) to excavate and resurface the
footway and carriageway. Works to be completed between 04 Jan 2022
and 14 Feb 2022 by Gilbert Ash/ Metro Traffic Services. Works to
take place Saturdays 8am - 5pm and Sundays 9am - 4pm. Weekdays will
be normal working hours of 9am - 6pm.
Weekend working required by Highways to
complete the works earlier, before the start of the next phase.
Noise levels provided for all machinery being used, Best
Practicable Means will be applied and tool box talks will be held
with all workers onsite to reduce the impact on residents and
ensure noise is kept to a minimum.
Option 1 -
Option 2 -
Option 3 -
Declarations: None
Contact: Emma Bourne, Environmental Health Manager Email: emma.bourne@woking.gov.uk Email: emma.bourne@woking.gov.uk.
Publication date: 10/01/2022
Date of decision: 23/12/2021